This is a live federal solicitation, open at publication (2026-08-19). Quotes are due September 16, 2026, 12:00 p.m. ET; a site visit is planned for August 24. Verify current status and amendments at the official source: SAM.gov — 140P4226Q0049. BidStroke is an independent writing service with no relationship to the National Park Service or the Department of the Interior.

Compliance matrix — RFQ 140P4226Q0049

Gazette entry · drawn from the published solicitation (66 pages + attachments) · back to the Gazette

Hazardous Tree Removal and Pruning — Richmond National Battlefield Park — National Park Service

RFQ 140P4226Q0049 · Total Small Business set-aside · NAICS 561730
Quotes due: September 16, 2026, 12:00 p.m. ET, by email
Questions due: September 9, 2026 · Site visit: August 24, 10:00 a.m. ET
Firm fixed price · Period of performance 9/21/2026 – 2/26/2027
Base CLIN + 2 option activities · LPTA · 2-file submission

A UCF-format solicitation (Sections A–M): the requirements live in Section C, the submission rules in Section L, and the award logic in Section M — lowest price technically acceptable, with every required document a pass/fail gate. Each line below cites the section that makes it. The defining feature: a missing document can end the evaluation regardless of price (L.1.2, M.2).

Submission mechanics — Section L and cover

RefRequirementFlagAnswer inDrafting note
L.1.2Quotes due no later than 12:00 p.m. Eastern on Wednesday, September 16, 2026, by email to the Contracting Officer, solicitation number in the subject line ("140P4226Q0049 RICH Hazardous Tree Removal" per L.1.2; the cover page words it "…RICH Hazardous Trees").MandatoryTransmittal emailNoon, not close of business. Multiple emails are allowed for file size, but all must land before the deadline; late means not accepted.
L.1.1Email only: mailed, shipped, faxed, or hand-delivered quotes are not accepted. The Government is not responsible for transmission failures.MandatoryTransmittalSend early enough to confirm receipt — the transmission-risk clause puts every failure mode on the offeror.
L.1.2Technical questions in writing to the Contracting Officer by September 9, 2026 (cover page states 12:00 p.m. ET). Questions after the date will not be addressed by amendment.Mandatory— (conduct)The two stated times differ (noon vs. close of business); treating noon as the deadline is the safe reading.
CoverSite visit planned for 10:00 a.m. ET, August 24, 2026 — meet at 1990 Maintenance Way, Richmond, VA 23231. Reservation not required.Optional— (conduct)Not mandatory, but the trees are marked in the field and mapped in Attachment 1 — seeing the access routes is what makes the pricing real.
L.1.5Two separate electronic files: File 1 — Factor 1 (Technical Capability) and Factor 2 (Contractor Compliance); File 2 — Factor 3 (Price), as an MS Excel workbook. File 1 must contain no pricing data.FormatWhole submissionPrice data in the technical file gets deleted by the CO before evaluation — don't make your compliance narrative depend on it.
CoverActive SAM registration required at time of award.MandatorySAM.gov recordFactor 2 additionally checks the registration lists NAICS 561730 as small — see below.

Required documents — Section L.2 (each one a gate)

RefRequirementFlagAnswer inDrafting note
L.2 F1-ATechnical approach document: capability against ALL work in Section C and attachments — understanding of constraints, risks, and challenges; site-specific approaches; materials and equipment. May use Attachment 3 (Quote Submission Package).MandatoryFile 1"Simple statements of compliance ('understood'; 'will comply')" are called out as insufficient in L.1.3 — describe the how, per site.
L.2 F1-BRelevant experience: three prior projects similar to ALL the work described, within the past five years (Relevant Experience Questionnaire, Attachment 3, or equivalent). Past performance checked in CPARS; "Satisfactory" or above is acceptable.MandatoryFile 1Similar to all the work — removal and pruning both. Non-federal projects count if the work is similar.
L.2 F1-CCopies of required licenses and certifications per Section C — the work must be under the direction and general supervision of an ISA-certified arborist (C.10.A), and at minimum the crew supervisor should be an ISA-certified arborist (C.9); arborist resume with education, experience, certifications required.MandatoryFile 1The ISA certificate and resume are the concrete evidence this sub-factor wants; crew composition minimums are in C.10.
L.2 F1-DBiobased certification: identify biobased products to be used per Section C, with percentage of biobased content — and state utilization or non-utilization explicitly. No response at all is technically unacceptable.MandatoryFile 1Even "no biobased products will be used" must be written down — silence fails the sub-factor by rule (M, Sub-Factor D).
L.2 F2-AContractor compliance: current UEI provided; SAM registration listing NAICS 561730 as a small business.MandatoryFile 1 (Attachment 3)Check the SAM record's size metrics before submitting — the evaluation reads the registration, not the assertion.
L.2 F2-BThree completed provisions submitted separately (not the SAM reps & certs printout): 52.209-7 Information Regarding Responsibility Matters; 52.209-13 Violation of Arms Control Treaties—Certification; 52.229-11 Tax on Certain Foreign Procurements.MandatoryFile 1The solicitation warns these may not be in SAM's reps & certs — complete the versions included in the solicitation itself.
L.2 F3File 2 — Price: SF 1449 signed by an official authorized to bind the company; all solicitation amendments acknowledged (SF 30 Block 11 methods); Section B price schedule completed for each line item — base CLIN 00010 (removal) and option CLINs 00020/00030 (pruning along roads / along trails).MandatoryFile 2 (Excel)Price every line item including options; both options carry an anticipated exercise date of 9/21/2026 (Schedule), and unpriced lines read as incomplete.

Performance requirements to price in — Section C

RefRequirementFlagAnswer inDrafting note
C.9OSHA 29 CFR 1910 adherence; adequate liability insurance and proper license to perform all work; contractor responsible for all permits and their expense.MandatoryTechnical approach + priceProof of insurance and business licenses is presented at award — but the coverage cost belongs in the price now.
C.10.D–FCrew list with positions, affiliation, training, and experience, submitted for NPS approval; each crew at minimum an ISA-certified supervisor, experienced climbers, experienced pruners; copies of all licenses/certificates within 10 calendar days after award.MandatoryTechnical approachName the crew in the quote where possible — an approvable roster beats a staffing promise.
C.11Equipment must meet OSHA/state/local safety requirements, be properly licensed, and be made available for inspection with certification documentation (e.g., annual ANSI/OSHA aerial-lift inspections, DOT trailer inspections) before use.MandatoryTechnical approachThe equipment table with inspection dates is cheap to include and directly answers the sub-factor A "materials and equipment" test.
C.12Safety: contractor responsible for safe conduct per 29 CFR 1910.266, subject to NPS Safety Officer inspection; site-specific safety plan prepared and submitted before work commences; own traffic control per MUTCD where operating along roads, with vested flaggers and two-way radios.MandatoryTechnical approach + priceTraffic control is contractor-furnished — a real cost on the road-pruning option line.
Att. 2Service Contract Act wage determination WD 15-4313 Rev 34 applies (Attachment 2, 7 pages).MandatoryPriceLabor priced at or above the WD rates with fringe — the arithmetic evaluators can check.
Block 8Period of performance 9/21/2026 – 2/26/2027; firm fixed price.MandatoryPrice + scheduleA winter window with weather-day language in Section C — lost rain time is credited to the schedule, not the price.

Evaluation — Section M (lowest price technically acceptable)

RefCriterionFlagAnswer inDrafting note
M.1Basis of award: LPTA under RFO FAR 12.203(c)(3) / FAR 15.101-2. Primary consideration is technical acceptability; required documentation not provided may be rated not technically acceptable regardless of price.Pass/failWhole submissionThere is no partial credit and no ranking — every gate above is binary, and price only matters after all gates pass.
M.3 F1Factor 1 (Technical Capability): Sub-Factors A–D each rated Technically Acceptable/Unacceptable; ALL sub-factors must be acceptable or Factor 1 is unacceptable.Pass/failFile 1Build File 1 as a checklist against L.2 in order — the evaluation table mirrors it exactly.
M.2If more than one offeror omits documents, the Government MAY request missing items — by email, on its own timeline, with no responsibility for mail landing in spam.Process—A discretionary safety net that only exists if several offerors fail together. Do not plan around it.

Annotated outline — the quote the matrix implies

File 1Technical capability and compliance
  • Technical approach per site (F1-A) · three-project experience sheet (F1-B) · ISA certificate + arborist resume + crew roster (F1-C) · biobased statement (F1-D) · UEI/SAM small-business note (F2-A) · three completed provisions (F2-B)

Six tabs, one per gate, no pricing anywhere. Attachment 3 (Quote Submission Package, 10 pages) is the government's own form for most of it — use it rather than reinventing the format.

File 2Price
  • Signed SF 1449 · amendment acknowledgments · Section B schedule: CLIN 00010 base removal, 00020 road pruning option, 00030 trail pruning option — as an Excel workbook

WD 15-4313 labor rates, MUTCD traffic control on the road option, equipment mobilization for a battlefield park's dispersed sites — the price defends itself only if these are visibly inside it.

Source and scope. Every line above is drawn from the published solicitation 140P4226Q0049 (66 pages) and its attachment list, cited by section. This page is BidStroke's independent decomposition of a public document; it contains no bidder's facts and is not guidance from, or endorsed by, the National Park Service. Always work from the official posting and any amendments: SAM.gov — 140P4226Q0049.